試題內(nèi)容

The method of calculating the EAC by adding the remaining project budget (modified by a performance factor) to the actual to date is used most often when the
A、Current variances are viewed as atypical ones
B、Original estimating assumptions are no longer reliable because conditions have changed
C、Current variances are viewed as typical of future variances
D、Original estimating assumptions are considered to be fundamentally flawed