宅男噜噜噜666在线观看,国产1区二区三区,国产日韩欧美大片,国产超碰97,国产自产视频,99久久国产综合精品色伊,亚洲午夜高清

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A manufacturing project is conducted under limited time constraints. At the point of delivery. A large batch of components must be scrapped, as they do not meet the industry minimum requirements.What should the project manager have done to prevent this problem?
A、Surveyed the industry standards and enterprise environmental factors.
B、Initiated quality audits to ensure that the planned quality assurance activities are followed
C、Increased the focus on risk identification, mitigation and contingencies.
D、Obtained approval from the sponsor to extend project time line.


相關(guān)試題

推薦文章