宅男噜噜噜666在线观看,国产1区二区三区,国产日韩欧美大片,国产超碰97,国产自产视频,99久久国产综合精品色伊,亚洲午夜高清

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(2)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A new project manager is assigned to a project that is already in progress. Because there are so many resources involved, the new project manager is confused about who does what. What document can the new project manager consult to clear their confusion?
A、Project organization chart
B、Organization breakdown structure
C、Responsibility assignment matrix
D、Resource breakdown structure


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容