宅男噜噜噜666在线观看,国产1区二区三区,国产日韩欧美大片,国产超碰97,国产自产视频,99久久国产综合精品色伊,亚洲午夜高清

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(1)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(1)》在線(xiàn)考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The actual cost of phase I is US$55,000, because additional resource skill sets were required to complete both deliverables I and 2. The deliverables and quality of the project are non-negotiable. Before the opening of phase II occurs, what should the project manager do?
A、Ensure there is a change management document approving the additional US$20.000 to the budget
B、Validate the project plan for phase its resource requirements
C、Determine how US$20,000 will be cut from phase II phase III
D、Determine which deliverables from phase II of phase 3 the stakeholders should reconsider


相關(guān)試題

推薦文章