軟題庫(kù) 培訓(xùn)課程
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Diagram 1 shows the sequence of activities for project XYZ and its duration. The project manager is asked to reduce the project duration by two weeks. None of the activities can be fast tracked. Activities A and F cannot be crashed, activity G can be crashed by two weeks; and all other activities can be crashed by one week. To meet the new project duration requirement, which of the following will the project manager decide to do?

A. Crash activity G.
B. Crash activity C and D .
C. Crash activity G, C and D .
D. Crash activity G,F and C .