試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

You’ve been assigned to take over managing a project that should be half complete according  to the schedule. After an extensive evaluation, you discover that the project is running far behind schedule, and that the project will probably take twice the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action?
A、Try to restructure the schedule to meet the project deadline .
B、Report your assessment to the sponsor.
C、Turn the project back to the previous project manager.
D、Move forward with the schedule as planned by the previous project manager and report at the first missed milestone.