PMP?當天每日一練試題地址:www.rydxd.com/exam/ExamDay.aspx?t1=33
往期PMP?每日一練試題匯總:www.rydxd.com/class/27/e33_1.html
PMP?每日一練試題(2022/12/30)在線測試:www.rydxd.com/exam/ExamDay.aspx?t1=33&day=2022/12/30
點擊查看:更多PMP?習題與指導
PMP?每日一練試題內(nèi)容(2022/12/30)
試題1
項目經(jīng)理決定采用一個主動接受戰(zhàn)略管理特定風險。項目經(jīng)理接下來應該怎么做?()查看答案
試題參考答案:B
試題解析與討論:www.rydxd.com/st/4913418608.html
試題2
項目發(fā)起人識別到,項目支出大大超出原計劃,項目發(fā)起人詢問項目經(jīng)理還需要多少資金才能最終完成項目,項目經(jīng)理應該使用什么來評估這個問題?查看答案
試題參考答案:D
試題解析與討論:www.rydxd.com/st/461904442.html
試題3
A product manager suggests design changes to add product value when compared with competitive products. These changes will benefit the company,but involve extra activities. What should the project manager do?查看答案
試題參考答案:B
試題解析與討論:www.rydxd.com/st/4804829321.html
試題4
在項目中,產(chǎn)品愿景將會驅(qū)動哪一個組件交付:查看答案
試題參考答案:A
試題解析與討論:www.rydxd.com/st/4250916323.html
試題5
公司決定為一個新項目實施敏捷,并成立一個敏捷團隊。為確保成功,應如何組織敏捷團隊?查看答案
試題參考答案:B
試題解析與討論:www.rydxd.com/st/5306588.html
試題6
During a demonstration, the customer provides feedback and requests a new;urgent enhancement due to a regulation change. What should the agile project manager do next?查看答案
試題參考答案:C
試題解析與討論:www.rydxd.com/st/4766718314.html
試題7
During project closure.the project manager finds it difficult t o obtain successful project completion feedback. Some stake holders disagree with the project's success criteria and have been frustrated with the project from the beginning. To what should the project manager refer to address these concerns?在項目收尾期間.項目經(jīng)理發(fā)現(xiàn)很難得到關于項目成功完成的反饋.一些相關方對項目的成功標準意見不一致.并從一開始就對項目感到沮喪。 項目經(jīng)理應查閱下列哪一份文件來解決這些問題?查看答案
試題參考答案:C
試題解析與討論:www.rydxd.com/st/4802822935.html
試題8
A project manager is leading a project to develop a new company-sponsored community event. There are several competing priorities and significant logical details. Since security is t he top priority,the project team contracts a security subject matter expert(SME).Together they create a risk matrix and discover that the overall risk level is lower than expected.Why was the overall risk score lower than expected?查看答案
試題參考答案:A
試題解析與討論:www.rydxd.com/st/477588581.html
試題9
After receiving a project management office(PMO)mandate that work packages must be performed by a preapproved offshore unit,the project manager updates the risk register. T o mitigate the risk of miscommunication between local and offshore teams,the project manager appoints an offshore coordinator as a single point of contact. What plan should be updated to describe the interactions between the two teams?在收到項目管理辦公室(PMO)規(guī)定工作包必須由一家預先批準的海外單位執(zhí)行后,項目經(jīng)理更新了風險登記冊,為了減輕本地和海外團隊之間溝通不暢的的風險,項目經(jīng)理任命一名海外協(xié)調(diào)員作為單一聯(lián)絡點.應該更新哪項計劃來描述兩個團隊之間的互動?查看答案
試題參考答案:D
試題解析與討論:www.rydxd.com/st/478548350.html
試題10
敏捷管理專業(yè)人士建議使用一些過程改進技術,但該技術導致速度降低并產(chǎn)生了一些質(zhì)量問題。團隊已經(jīng)進行修正,但是職能經(jīng)理很不高興,此時應該怎么做會避免這樣的結果?查看答案
試題參考答案:B
試題解析與討論:www.rydxd.com/st/5296426926.html
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |